BVI News

ESHS won’t be ready for start of new school year in September

Premier Dr Natalio Wheatley said the Elmore Stoutt High School will not be ready for the original September completion as was planned.

The Premier sought to clarify his previous statement regarding the September deadline stating people have been ignoring the fact that he said there would be a slight delay, and everyone involved was pushing for late September instead of the beginning of September.

“Unfortunately, soon after that statement was made, the RDA received information that the windows and the doors were delayed. But the good news is that the windows and doors – at least some of them – have been received. I was very happy and relieved to hear that,” Dr Wheatley said.

“The contractors and the RDA are working assiduously to get the school open as quickly as possible. Obviously, it won’t be ready for the original date, but the Minister for Education today will give a very detailed update on where we are not only with Elmore Stoutt but with all the schools in the territory,” the Premier added.

Dr Wheatley also addressed the negative comments from members of the communities about the school.

“We tend to as a community sometimes seek to focus on the negative. On the Elmore Stoutt High School campus, we have not had a new building since Lavity Stoutt was alive. That L Adorothy Turnbull building – that was built when I was in high school. Nothing has been built since then. We have established I believe three buildings there that will help meet the needs of the students,” the Premier said.

“If it is late a month or a few weeks, certainly we can’t let that overshadow the fact that the students would have more accommodations and be able to shift from the Clarence Thomas building in Pasea. It is a warehouse. It is not designed to be a school. Certainly, that is progress, and I certainly will not let any person dampen my spirit for the progress that has been made on that project which is really record time,” he added.

Shares

Copyright 2024 BVI News, Media Expressions Limited. All Rights Reserved. This material may not be published, broadcast, rewritten or distributed.

54 Comments

Disclaimer: BVI News and its affiliated companies are not responsible for the content of comments posted or for anything arising out of use of the comments below or other interaction among the users.

  1. Better late than never says:

    I’m just glad that the students will have better classrooms to sit in. It is long overdue.

  2. ... says:

    STF up dude

    Like 6
    Dislike 8
  3. Lmaoo says:

    Is this news to us?? Like we didn’t know this

    Like 33
  4. Dede says:

    I could have told you this. Even a blind person saw this. Said this the other day, it’s best to take time and build it properly and meet all the building codes and standard than to rush it and later have to pay millions to repair and in some case may have to demolish and rebuild.

    On a serious note thou, it time for us to put aside our political differences and pay serious attention to our education and healthcare systems. When I said us I’m referring to our elected official and the citizens/resident of this country. We need to stop accepting lip service and mediocre performance. If they not up to it, remove them and give someone else a chance. We need to recognize that those who created these problems cannot fix it since the cannot accept they are wrong.

    Remember a educated and healthy nation builds security, prosperity and a peaceful nation. Everyone benefits from this.

    Like 41
    Dislike 2
  5. heckler says:

    He flip-flopping

    Like 11
  6. Guest says:

    Noooooo….really???shocked…..

    Like 13
    Dislike 1
  7. lie too doggone much says:

    We knew from day 1 that it couldn’t be done….Who fooling who?

    Like 20
    Dislike 1
  8. People over politics says:

    Slowande lied and was caught he must go fast

    Like 21
    Dislike 6
  9. What!!!! says:

    Did anyone besides government ministers think that it would be open when they said it would?

    Like 17
    Dislike 1
  10. It going open my people says:

    Premier the Government just need to proceed and get the school open. An extra month ain’t going to kill nobody. Don’t mind the noise.

    Like 9
    Dislike 1
  11. Sherlock says:

    No s**t

  12. No surprise says:

    Construction of the ESHS should have commenced in 2018 but the NDP was still in shock from Irma.

    Like 12
  13. Vg boy says:

    Look how fast it’s being built. England got the moving like soldiers now dat everything being watched

    Like 5
    Dislike 1
  14. Moses says:

    Our children’s education should come first. Ahead of the $7.2m airline, the $100m pier , the $500m net jet runway extension.

    Like 10
    Dislike 4
  15. Uneducated says:

    Any body with simple common sense would know that was no where near ready for September sad judgment

    Like 12
  16. Positive Vybes says:

    It could have been ready if the shipment of the windows and doors were not delayed. You all are too negative. Sickening!!

    Like 4
    Dislike 25
  17. Hmmm says:

    What’s the difference between September and October, Weeks! It’s done

    Like 2
    Dislike 6
  18. Mick Mars says:

    Any competent contractor knows that windows and doors have a lengthy time-line to being made and shipped so the whole “there was a slight delay” thing is rubbish because even if they were on time, they still wouldn’t constitute a complete building since you’ve no word on the furnishing inside, muchless the other electronic resources to teach properly.

    Just like they will yell you that the “school” will be finished without ever mentioning that it’s only a shell, they will continue to misconstrue the truth hoping that you’ll give them the benefit of the doubt and give them passing marks.

    Political ploys and talking points while playing with our children future.

    Like 22
  19. Wendy says:

    No shit! Like we all knew it wasn’t going to be ready for Sepetember. Slowendo needs to be acutely aware of injecting the technological infrastructure for AI. Artificial Intelligence is here! Not tomorriw or some intangible, future date……NOW!
    Yes, holograms, everything will become digitized and ‘eye based.’ Our world is about to change as we know it….another ‘paradigm shift’ in the evolution of education.
    Heads up folks, the future is now!
    We are we going to do????
    WAKE UP EVERYONE, OUR PRECIOUS CHILDREN’S FUTURE LIES IN OUR HANDS!

  20. Lodger says:

    Surprise! Surprise!

  21. hmm says:

    that wont finish untill november, finishing work takes more time

  22. Delay says:

    Windows and doors are the delay. Well thats what happens when you give a million dollars to a pissant company.

    Like 3
    Dislike 3
  23. Dert says:

    What makes you think that will happen?

  24. Not2Sure says:

    Five years since Irma. Five years. And still we have no High School yet.

    Like 6
    Dislike 1
  25. BuzzBvi says:

    Hmmm. What is the difference?? The school year doesn’t start in October.

  26. JAY-Z says:

    From time they said it, i said no way, it’s not going to be ready by that time. Smh

  27. Anonymous says:

    He sounds just like the drug smuggler he replaced with his ” shut up” comment

  28. Deh Watcha says:

    This doors and windows delay excuse doesn’t really mean much to the common man on the street since none of us knew when they were scheduled to arrive anyway. None of us has seen the works programme schedule. The door and window installation on the programme schedule would have been based on the lead times supplied by the suppliers. So something ain’t right there.

    Doors, windows and hardware are long lead items (always have been). Especially when hurricane rated glass is involved. Some companies also have strict order schedules and I doubt they will bump an order worth millions for one in the hundreds of thousands.

    Lead times can sometimes be upwards of 4 to 6 months. For these to have arrived on time they would have had to be ordered before construction started or on day 1.

    We are paying loads of money to persons providing poor management. But hey we are now saving $300k per year so it’s alright.

  29. WEW says:

    But But we were promised ! Another SNAFU

  30. Jealous says:

    You sound jealous you didn’t get the job

  31. Lily ann says:

    Dude, stop saying bout windows and doors delay. This structure MISSING a whole lot of things. You should’ve never made the call that the school would be open for Sept. The public and all Governing better than u. Goes to show u ain’t got no vision, not even vision and common sense to see that these building will need monthssss more to be finished !!

  32. Wall watcher says:

    The $1mil wall didn’t get finished yet either…. Whappen? -money done ?

  33. Omegacaribbean 3404875 says:

    To all the leaders We have materials in stock to get this job completed aluminium frames with laminated safty glass and commercial design doors in stock.

    Like 3
    Dislike 1
  34. #1 says:

    THE EDUCATION SYSTEM IN THE 21 CENTURY REFUSE TO ENLIGHTEN THEMSELVES ON AS SIMPLE WHAT IS AN ISLAND ? ( LAST TIME I CHECKED LAND SURROUNDED BY WATER IS AN ISLAND / AND PEOPLE FROM OTHER CARIBBEAN COUNTRIES ARE CALLED ( ISLAND PEOPLE ) ? , ALL OF OUR ANCESTORS CAME FROM AFRICA ON THE SAME SLAVE SHIPS / FAMILIES WERE SEPARATED AND SENT EVERYWHERE , SO THAT ALONE SAYS IT ALL , AND NONE OF THESE HIGHLY EDUCATED ARISTOCRATS ARE HAVE THE DECENSY TO THROW THAT EVIL MENTALITY IN THE GABBAGE ( BUT THEY HOLLERING OUT RACISM / COLONIALISM LIKE JUST DISCOVERED IT ?

  35. Nah says:

    This project 5 years behind schedule not a couple months or weeks

  36. School Children says:

    School Children knew that the School for Children would not be finished on time. Still, our un-elected miss-management committee (government) continued to tell us lies until they simply couldn’t lie about it being ready, anymore. Then they told us different lies about delayed windows. FFS they really, really believe we are stupid.

  37. Doors and Windows says:

    Doors or windows here or there. Please plan to finish and furnish the building by the end of November so that it can be ready for the beginning of the next term. Ensure all the kinks are be ironed out in December and have an orderly start to next school term in January 2023. Transfer the Althea children to Clarence Building while the old Althea building is demolished and rebuilt for the next school year.

  38. Foolishness says:

    But still it took 3 1/2 years to start it since they got elected. Get away from here with your stupid nonsensical cult story.

  39. Thanks you says:

    While you’re at it get back the 8 million paid to the COI lawyers. Get back the 17k per day for 3 barges for 6 months. Get back the 20 million given time the fake fishermen and farmers. Get back the 786k spent on the AC in the complex. Get back the 40M from social security that we haven’t seen the benefit of yet. Check on all of this one time. Please and thanks.

    Like 4
    Dislike 1
  40. Sense says:

    Obviously, it should have started in 2018. It’s now 2022. The pledges and expertise were there and refused for nefarious reasons.

    We also need to see send in moving the HOA and court to something purpose built perhaps in the land near the government building. This would free up more space for the school to flourish as well as providing a fit for purpose facility for our government and courts of law.

  41. Sense says:

    Obviously, it should have started in 2018. It’s now 2022. The pledges and expertise were there and refused for nefarious reasons.

    We also need to see send in moving the HOA and court to something purpose built perhaps in the land near the government building. This would free up more space for the school to flourish as well as providing a fit for purpose facility for our government and courts of law

  42. Simon says:

    Are you not forgetting some things like the $40M taken from social security and handed our to so-called fisher men and farmers as well as businesses that have been inoperable for decades. Oh there is also the $3M paid to badges to catch go fast vessels.

  43. Elsa says:

    Positive vibes, you confirmed their point. One cannot say fir certain that buildings in the condition of the schools (with no windows and doors) will be completed if he/she has no control over certain things such as the shipment of goods.

  44. Lilly says:

    I fir sure though everything was on sight when those promises were made.

  45. Sight says:

    Premier and Minister, do not allow anyone to tell you nonsense and you repeat it to the public. It was obvious the school would not be completed, even a small child could see that. In the end you will look bad. It is better to surprise the public and finish earlier than declared than to attempt to raise expectations gving an unrealistic date and then disappoint.

  46. Butting Head says:

    The school will be ready for January 2023 earliest. If electrical wires aren’t yet pulled it will be extended. so be prepared for online schooling, which could be instant,

  47. Hmmmmm says:

    Thos looks like a over crowded prison cell block. It is me or the view have them choking against one another. They seems so close to each other.

    Like 3
    Dislike 1
  48. hush says:

    Rome wasn’t built in a day

    Like 1
    Dislike 2
  49. Guess What? says:

    I wonder if all decent persons in this Country have gone to permanent sleep, leaving the open space for negative comments all the way. Virtually all comments are toxic as if the Premier is demon possessed, chronic illiterate and block headed. For God’s sake, this gentleman has a PhD and has produced great minds at HLSCC over the years. Whatever you blog here is read worldwide. Over the years its always toxic comments most of the time as if we are at war with ourselves. These people are doing their best in the circumstance. If you think you know better and can do it better, wait for next election and contest. Why are we running rouge to kill all the chicken on the street simply because the government wanted to please the people by putting the ESHS project on a tight construction project. Orders were placed for materials and delivery dates were secured but it turned out that suppliers turned around to requested for more time. People, criticism should be constructive and not destructive. Anything less than good advice to these leaders to assist them in making better decision going forward is evil.

    Like 3
    Dislike 3
  50. How the budget looking.. says:

    That’s what we need to know as of now, is the budget under, over or on par.I know a lot of money and time went into the rush to have it done for September.

  51. Education Dept says:

    Speaking about vibes. Why on God’s earth the school continues to make parents pay for a stupid VIDE that teachers DO NOT USE and just to collect dust. Some parents have it very hard to come up with this money for this archaic device just for the school to con them out of their hard earned money. But then again, I heard that it’s the Ministry that forces it on the parents as a money making scheme/racket.

  52. Scapegoat says:

    The windows and doors excuse is a scapegoat by RDA and politicians because other aspects behind. Stop throwing people under the bus for you not doing your job!

  53. Just saying says:

    Looking at this picture, let Facebook reality, the ESHS still will not be finish by October, more like November.
    The building still need to print, plus light fixtures, the flooring need to be done, plus plumbing fixtures need to be install, Just saying.

Leave a Comment