Gov’t using international standards for Paraquita Bay road project
Communications and Works Minister Kye Rymer said the government is following international standards on road construction, even as it grapples with major delays on the stretch of road between Paraquita Bay and Hodges Creek.
Rymer addressed concerns about the width of the new road. He explained that the old road ranged between 22 to 28 feet wide and the completed road will be approximately 26 to 28 feet, inclusive of drainage works.
“The actual roadway will be 22 feet in width,” he said, noting that the finished project will give the impression of a wider road. He added that this is consistent with international guidelines, where standard lane widths are approximately 11 feet in Europe and 12 feet in the United States.
The project, which began in September 2024, has been delayed by nearly a year. Rymer explained that early challenges, including flawed design work and conflicting survey data, led to a ‘real world’ six-month suspension of work.
“Deficiencies in original design and inaccuracies in the survey data led to a six-month suspension of works in 2024 as the designs had to be redeveloped and corrected to reflect accurate site conditions,” Rymer stated.
He added that there were “discrepancies between the survey data held by the Public Works Department and that provided by the contractor,” as well as changes to the road elevation that required modifications to the engineering designs.
The minister also pointed to land access issues during construction. “The project faced relief issues with some property owners that required resolution during the execution of the project,” he explained.
Despite the delays, Rymer said the works were necessary to “ensure the integrity and long-term viability of the infrastructure being delivered.”
Eighth District Representative Marlon Penn pressed Rymer on the lack of preparation ahead of the project. “Can the Minister confirm issues like relief, survey data and the likes, aren’t those things that should be ironed out before a project even goes out to tender?” he asked.
Rymer admitted the oversight, stating, “I do agree… I would presume that those things would have been done, but we were faced with them. Moving forward, we would know to do better due diligence.”
When asked if the project was poorly managed from the start, Rymer responded, “We’ve acknowledged that there were some delays. We acknowledge some of the challenges. These are things that happen in the real world. You learn from these things and you definitely move forward.”
Copyright 2025 BVI News, Media Expressions Limited. All Rights Reserved. This material may not be published, broadcast, rewritten or distributed.
Definitely a humble man and he knows its alot but he is definitely taking accountability
for road construction require contractors with EXPERIENCE constructing roads to these standards. Appears no contractor has that level of experience on this project; hence all the mistakes, delays, land controversies, etc.
YALL NEED To HURRY TF UP….. I tired breathing in that dust but ain’t like yall care
so that is why the cutter went back out sections of the concrete? you een tired leading the masses wrong?
International standards yuh say. Which country? The width of these new roads being build are for Mini Coopers. We need roads for local standards.
complete b.s, if we were using international standards a road of this size wouldn’t take 8 months and counting to complete
so when will it be completed?
International standards dictate that the newspaper road is for one way traffic with turning lanes. How is it the contractor got it so narrow with no pull off. I am so disappointed.